• Hausa Edition
  • Podcast
  • Conferences
  • LeVogue Magazine
  • Business News
  • Print Advert Rates
  • Online Advert Rates
  • Contact Us
Saturday, October 25, 2025
Leadership Newspapers
Read in Hausa
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
Leadership Newspapers
No Result
View All Result

‘CBN’s N122.223bn Power Intervention Projects Ready Next May’

by Kayode Ekundayo
2 years ago
in Business
CBN
Share on WhatsAppShare on FacebookShare on XTelegram

The much anticipated Central Bank of Nigeria (CBN)’s power intervention projects will be ready by May, 2024, according to Project Management Office, Transmission Company of Nigeria (TCN), Engr. Engineer Matthew Ajibade, 

Advertisement

The N122.223 billion projects, which cut across the states of the federation, aim to resolve the transmission and distribution interface bottlenecks to improve supply to end users and unlock the unutilised generation capacity in the country.

Ajibade, who led the CBN, Nigeria Electricity Regulatory Commission (NERC), NESI and other stakeholders on tour of the projects sites in Lagos on Wednesday, noted that, manufacturing process for most of the contacts is scheduled to be completed early next year 2024 to pave way for shipment and delivery.

Advertisement

The projects, when completed, will enhance delivery of about 1,500MW of power nationwide.

Recall that the Central Bank of Nigeria (CBN) had, in August this year, approved the sum of N122,289,344,369.39 for intervention in the nation’s power sector.The loans were accessed by the 11 electricity distribution companies at 9 % interest rate from the Central Bank of Nigeria(CBN).

According to Ajibade, so far, N85.4billion of the approved sum had been disbursed to 53 contractors to execute the projects.

RELATED NEWS

Investing In Braided Wigs For Profit

NIWA Begins Clearance Of Water Hyacinth On Lagos Waters

‘Investment Banking Firm Emerges Best Issuing House’

Policyholders To Submit NIN, BVN Before Insurance Contract Activation

Already, 10 of the power transformers have been delivered while the rest ranging from 150MVA, 100MVA and 60MVA are expected to be delivered and installed on or before May 2024.

“This intervention is anchored on firm Service Level Agreements (SLAs) between TCN and DisCos on the one hand and DisCos and their customers on the other hand. The facility was given to Discos to invest in TCN Networks by virtue of NERC regulation that permits third party investment in the Electricity Network. 

Payment for the loan would be a net off from the TCN monthly invoice to DisCos. The project implementation Office (PMO) is resident in TCN for effective implementation”, he stated. 

However, seven contractors that have finished with offshore production process are; Skipper Nigeria Ltd (BEDC), GTA Engineering Nigeria Limited for PHEDC network, T&D West Africa Ltd (IKEDC), Lagacee Power Ltd (AEDC), Bussdor & Company Ltd (AEDC) FOSAB Global Energy Services Limited PHEDC and Beam Energy Ltd (EKEDP). 

Some consignments containing Power Transformers have been delivered to Gwagwalada, Oworonsoki 132/33KV Substation and TCN Ojo store in Lagos by Contractors.

CBN’s representative and Assistant Director/ Head Infrastructure Finance Office, Tumba Abdulrazaq Tijani, applauded the commitments of the contractors, saying, execution of the projects within a short time of accessing funds surpassed the bank’s expectations.

He noted that the projects, when completed, will impact positively on electricity deliveries by discos to consumers across the country.

The projects include eight 150MVA, 19 of 100MVA, 67 of 60MVA, three Re-conductoring existing Transmission lines (Conductors & Accessories) of 517.5 km, 24 contracts for upgrading Existing 132/33KV Substations and construction of 50 of 33KV line bays.

Join Our WhatsApp Channel

Breaking News: Nigerians at home and abroad can now earn in USD by acquiring ultra-premium domains from $3,000 and profiting up to $36,000. Perfect for professionals. Click here.

SendShareTweetShare

OTHER NEWS UPDATES

Investing In Braided Wigs For Profit
Business

Investing In Braided Wigs For Profit

15 hours ago
‘NIWA Lacks Fund, Manpower To Regulate Inland Waterways’
Business

NIWA Begins Clearance Of Water Hyacinth On Lagos Waters

15 hours ago
‘Investment Banking Firm Emerges Best Issuing House’
Business

‘Investment Banking Firm Emerges Best Issuing House’

15 hours ago
Advertisement
Leadership join WhatsApp

LATEST UPDATE

Constitution Review: NASS Joint Committee Approves Additional State For South-East

38 minutes ago

Manchester United Edge Brighton In 6-goal Thriller For Third-straight Win

45 minutes ago

PICTORIAL: 20 Years After, Obasanjo Celebrates Stella, Says Ex-First Lady Served Humanity

48 minutes ago

Kano Hisbah Cancels Court-ordered Marriage Between TikTokers

52 minutes ago

PDP Convention: Jegede, Oyinlola, Udenwa, Others To Screen Aspirants Tuesday

58 minutes ago
Load More

© 2025 Leadership Media Group - All Rights Reserved.

No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us

© 2025 Leadership Media Group - All Rights Reserved.