• Hausa Edition
  • Podcast
  • Conferences
  • LeVogue Magazine
  • Business News
  • Print Advert Rates
  • Online Advert Rates
  • Contact Us
Friday, October 24, 2025
Leadership Newspapers
Read in Hausa
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
Leadership Newspapers
No Result
View All Result

North-East Electricity Outage: TCN Reaffirms May 27 Restoration Timeline

by Nse Anthony - Uko
1 year ago
in Business
TCN
Share on WhatsAppShare on FacebookShare on XTelegram

The Transmission Company of Nigeria (TCN) has reaffirmed its commitment to restoring electricity to the North-East on May 27 as earlier stated.

Advertisement

The company made the affirmation in response to the concerns raised by the North East Governors Forum (NEGF) at its 10th meeting in Bauchi on Saturday, alleging that the region had been neglected in infrastructural development.

TCN’s general manager, Public Affairs, Ndidi Mbah who disclosed this in a statement she made available on Tuesday said, the work is already at an advanced stage.

Advertisement

Mbah said, the company is unaware of the significant difficulties and challenges the lack of power supply poses to the areas, and the concerns of the governors for their people and the day-to-day running of governance and businesses.

However, she noted that the company has been working tirelessly to rebuild the four towers destroyed by the vandals, and would not rest until power is restored to the affected areas.

She, therefore, appealed for a little more patience, as work is truly advancing, adding that the company is pushing its contractors very hard to ensure that it delivers on its promise of rebuilding the towers and energising the transmission line.

RELATED NEWS

Lagos Waterways Authority Begins 5th Edition Of Water Savvy Kids’ Programme

New Tax Reforms Promise Relief, Deepen Regulatory Clarity For Real Estate Sector

Embrace Integrity, Innovation, Customs Urge Promoted Officers

Minister Hails First African Free Trade Agreement Exporter

She affirmed that “despite the recent increase in vandalism, we have continued to rebuild towers each time they are damaged and have consistently restored supply. The four vandalised towers on the Gombe axis are no exception. Despite our prevailing poor liquidity, we have mobilised all necessary resources to ensure this job gets the attention it requires.

“To expedite the work, we have insisted that the contractor put in place on-site machines that will help increase the fabrication processes of tower members which is ongoing. A visit to the site will show that the towers are nearing completion, with one tower at 90 per cent completion, another at 80 per cent, a third at 60 per cent, and the fourth at 40 per cent.

“We are utilising all available daylight hours for the work. However, due to security issues, we are unable to work through the night, which we would have gladly done. Nevertheless, we are optimistic about completing the reconstruction and energising the line within the given time frame. We expect power supply to be restored by May 27, 2024, through the new 330kV transmission line, allowing Yola and Jos DisCos to offtake and distribute optimally from TCN substations.

“Again, we appeal for your patience and sincerely assure you that we are working very hard to complete the work within the timeframe. It is our joy to serve you and the nation at large, and we would be truly happy and grateful to God for the quick completion of the work. Please bear with us”, she said.

 

Join Our WhatsApp Channel

Breaking News: Nigerians at home and abroad can now earn in USD by acquiring ultra-premium domains from $3,000 and profiting up to $36,000. Perfect for professionals. Click here.

SendShareTweetShare

OTHER NEWS UPDATES

Lagos Waterways Authority Begins 5th Edition Of Water Savvy Kids’ Programme
Business

Lagos Waterways Authority Begins 5th Edition Of Water Savvy Kids’ Programme

22 hours ago
Firm Advises Real Estate Investors To Prioritise Land Title Documents
Business

New Tax Reforms Promise Relief, Deepen Regulatory Clarity For Real Estate Sector

22 hours ago
Customs CG Approves Promotion Of 357 Junior Officers
Business

Embrace Integrity, Innovation, Customs Urge Promoted Officers

22 hours ago
Advertisement
Leadership join WhatsApp

LATEST UPDATE

Deputy Speaker Kalu To Be Honoured At Peace Achievers International Awards 2025

7 minutes ago

Private Schools Must Upgrade Or Risk Closure – Proprietors

7 minutes ago

Group Urges Delta Women To Key Into Govt Programmes, Voter Education

8 minutes ago

Experts Call For Revival Of Indigenous Knowledge System

9 minutes ago

No Fatality In Aba Building Collapse – Authority

10 minutes ago
Load More

© 2025 Leadership Media Group - All Rights Reserved.

No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us

© 2025 Leadership Media Group - All Rights Reserved.