• Hausa Edition
  • Podcast
  • Conferences
  • LeVogue Magazine
  • Business News
  • Print Advert Rates
  • Online Advert Rates
  • Contact Us
Wednesday, October 29, 2025
Leadership Newspapers
Read in Hausa
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
Leadership Newspapers
No Result
View All Result

Why Past Roads Failed The Test Of Time – Umahi

by Tarkaa David
16 hours ago
in News
Tinubu
Share on WhatsAppShare on FacebookShare on XTelegram

The Minister of Works, Engr. David Umahi says the president’s administration is rebuilding almost all roads across the country because roads constructed over the past 30 years have been substandard, requiring each to be worked on.

Advertisement

During Tuesday’s inspection of the Abuja-Kaduna highway, the Minister blamed the failed roads on the construction model.

He said this is evident in sections of the Julius Berger construction company’s completed projects on the Abuja-Kaduna highway, which have developed potholes.

Advertisement

“The construction method is one of the problems because you can find out that they removed the asphalt when Berger was doing the job. They said they want to grind it with laterite. It’s not a good construction method because they brought new litter on the road. This road, there’s the California Bearing Ratio, the CBR and the strength of the sub-base. So when you remove this and bring fresh latrite, the compaction and consolidation will not be as strong as the one that has consolidated over the years. And so it is bound to fail. And that’s why you see that what Berger completed was beginning to see failures, even while they were constructing.”

“Asphalt has a shelf life of 25 years. And so, after 25 years, the cost of wearing has decreased. I want Nigerians to know this. All our major roads, whether Lagos-Ibadan, East-West Road, Abuja to Kano, or Lokoja, Enugu-Onitsha, or Enugu to Port Harcourt, name them, no administration has not worked on these projects. And the question you will ask is why?

 

RELATED NEWS

House Of Reps Okays $2.34bn Loan Request For Tinubu

Resist Moves To Divide Nigeria, VP Shettima Tells Arewa Leaders

Drama As JAMB Officials Walk Out On Reps Committee Members

NDLEA Arrests 45,853 Suspects, Secures 9,263 Convicted In 30 Months

“The reason is our construction method. That’s why I tagged it as President Bola Tinubu not constructing roads. He’s building roads.”

He, however, said the president is stopping this practice with the Abuja-Kaduna-Kano highway that will last for 50 years.

While assuring that section 1 of the project will be completed before the scheduled 12 months, it should be completed by February.

He said Section 1 starts from 4 kilometres into Kogi and ends at Katari. While Section 2 will also go ahead with that.

“The president has paid over 120 billion naira on this first contract, which shows commitment and love for the country’s people, especially our northern brothers and sisters.”

“This project, the first project, N252 billion, comprises about 118 kilometres of roads, 86 kilometres of concrete, and 17 kilometres of wearing course in Kano. We have about 6 kilometres dualised, which is an addition by Mr President at the end of the Kano section, an additional six by 2, that’s 12 kilometres.”

“Today, about 2 kilometres have been done on those 17 kilometres. The 6.6-kilometre by two is completed in the Kano section. They are putting solar lights there now.”

“On the 86 kilometres, we’ve completed about 26 kilometres of asphalt. So, we have 60 kilometres. Now, the commitment is that this road, the first contract, is supposed to last till April 2026, that’s 14 months. And that’s the promise we publicly made to Mr President in the Federal Executive Council. But our commitment now is to start in February. So, by February of next year, it will be 12 months. So, we will finish the first contract by February 2026.”

Join Our WhatsApp Channel


SendShareTweetShare

OTHER NEWS UPDATES

Editors Shift Annual Conference, Tinubu Plans Attendance
News

House Of Reps Okays $2.34bn Loan Request For Tinubu

19 minutes ago
Resist Moves To Divide Nigeria, VP Shettima Tells Arewa Leaders
News

Resist Moves To Divide Nigeria, VP Shettima Tells Arewa Leaders

20 minutes ago
UTME: JAMB Cancels Registrations Of 817 Candidates Over Infractions
News

Drama As JAMB Officials Walk Out On Reps Committee Members

1 hour ago
Advertisement
Leadership join WhatsApp

LATEST UPDATE

House Of Reps Okays $2.34bn Loan Request For Tinubu

19 minutes ago

Resist Moves To Divide Nigeria, VP Shettima Tells Arewa Leaders

20 minutes ago

Vinicius Jr Apologises To Real Madrid Fans After Substitution Spat

58 minutes ago

NPF Celebrates 70 Years Of Women In Policing

59 minutes ago

CAF Announces Dates, Venues For 2026 FIFA World Cup Playoffs

1 hour ago
Load More

© 2025 Leadership Media Group - All Rights Reserved.

No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us

© 2025 Leadership Media Group - All Rights Reserved.