Minister of the Federal Capital Territory (FCT), Nyesom Wike, has expressed satisfaction with the quality and speed of the ongoing road construction in Kuje, Kuje Area Council of the territory.
Wike who stated this after he inspected the road projects in Abuja, explained that the five-kilometre dual carriage way from Garage Junction to LEA Secretariat was nominated by the council’s chairman and stakeholders in the area.
The roads included the six-lane dual carriageway from Airport Expressway to Kuje Junction and the five-kilometre dual carriageway from Garage Junction to LEA Secretariat, in Kuje.
The minister said the contractor has done earth work covering 2.5 kilometres, adding that what would follow was the drainage.
“The contractor has agreed that the road will be completed before the end of the year. We are very impressed.
“The one from the Airport Expressway to Kuje Junction is a six-lane dual carriageway, being handled by Arab Contractors.
“As you can see, the work is going on very well and we are quite satisfied with the quality of work so far.
“The contractor has promised to complete all the earth work before the end of the year. This is very interesting news to us, indicating that we will reach our target by the end of the year,” Wike said.
Earlier, the executive secretary, Federal Capital Development Authority, Mr Shehu Ahmad, said that the road, linking the Airport Expressway to Kuje Town would cover 11 kilometres.
Ahmad explained that between the airport expressway to Kuje junction, the road would cross over two rivers and also cross over the Outer Southern Expressway that would link the city centre with Gwagwalada Expressway.
He added that the Airport Expressway to Kuje Junction would cover nine kilometres, while the remaining two kilometres would extend backward towards Kyami District.
He explained that one of the major constraints affecting the delivery of the road was the presence of five towers belonging to the Transmission Company of Nigeria (TCN) along the road corridor.
The FCDA boss added that TCN have been contacted and have agreed to relocate the towers, stressing that until the obstructions were removed, work could not take place in the affected areas.