• Hausa Edition
  • Podcast
  • Conferences
  • LeVogue Magazine
  • Business News
  • Print Advert Rates
  • Online Advert Rates
  • Contact Us
Monday, October 6, 2025
Leadership Newspapers
Read in Hausa
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
Leadership Newspapers
No Result
View All Result

Federal Gov’t Threatens To Terminate Road Projects In Kogi Over Delay

by Tarkaa David
2 months ago
in News
Share on WhatsAppShare on FacebookShare on XTelegram

The federal government has issued a 30-day notice of termination to contractors handling the rehabilitation of Lokoja- Shintaku – Dekina – Anyigba Road and the reconstruction of Okene – Ajaokuta – Itobe dual carriageway in Kogi State over delay by the contractors.

Advertisement

Minister of Works, Engr. David Umahi, disclosed this on Wednesday after a meeting with the contractors at his office in Abuja.

A statement by the Special Adviser on Media to the Minister, Barr Orji Uchenna Orji, said Engr Umahi reached a mutual agreement with the contractors handling the projects in Kogi State on the way to the projects which were awarded in 2022 to CCECC Nig Ltd and TEC Engineering Company Nig Ltd with completion timeline of 2024.

Advertisement

According the statement, the Minister frowned at the delay by the contractors in achieving key deliverables of the projects within the timelines and financial resources made available by the federal government.

On the contract for the rehabilitation of Okene- Ajaokuta – Itobe carriageway in Kogi State bring handled by CCECC Nig Ltd, the minister noted that the project was awarded in 2022 with a length of 52.27km but the contractor has only achieved 1.97% completion (binder) on one alignment despite receiving ₦2.5 billion advance payment.

“He therefore directed the Director Highway North Central to issue a warning letter to the contractor to resume work on the site within 30 days using the old rate to achieve a milestone that is commensurate with the money they received, after which the balance of the job yet to be done would be mutually terminated to enable the Ministry procure the remaining section of the project for enhanced funding and execution,” he said.

RELATED NEWS

Attacks: Kwara APC Elders Mourn Victims

Trump To Host Historic UFC Fight On 80th Birthday In White House

‘Alake, A Dependable Ally, Consummate Strategist’, Tinubu Hails Minister At 69

7m Children To Receive Measles, Rubella Vaccines In Kano

Furthermore, on the rehabilitation of Lokoja- Shintaku – Dekina – Anyigba road awarded to TEC Engineering Company Nig Ltd, the Minister noted that the contract was awarded in 2022 but recorded only 1.04% completion despite receiving ₦1 billion as advance payment.

“It was directed that the contractor should lay 3km asphalt by December 2025 after which a final account would be made based on the milestone completed and the job would be terminated on mutual basis,” he added.

The Minister, further directed that the assessment for the funds already released shall be based on the old rate while the assessment for the funds to be accessed under the year 2025 budget shall be based on the new rate.

“The Minister also directed that the consultancies for both contracts be mutually terminated pending when a new contract is procured on the projects,” the statement said.

Join Our WhatsApp Channel

SendShare10199Tweet6375Share
Tarkaa David

Tarkaa David

OTHER NEWS UPDATES

Nigeria @64: Nation Building Requires Collective Efforts, Says Kwara Gov
News

Attacks: Kwara APC Elders Mourn Victims

7 minutes ago
trump
News

Trump To Host Historic UFC Fight On 80th Birthday In White House

11 minutes ago
Solid Minerals Get Only N24bn Capital Budget Despite Needing N250bn
News

‘Alake, A Dependable Ally, Consummate Strategist’, Tinubu Hails Minister At 69

13 minutes ago
Advertisement
Leadership join WhatsApp

LATEST UPDATE

Attacks: Kwara APC Elders Mourn Victims

7 minutes ago

Trump To Host Historic UFC Fight On 80th Birthday In White House

11 minutes ago

‘Alake, A Dependable Ally, Consummate Strategist’, Tinubu Hails Minister At 69

13 minutes ago

7m Children To Receive Measles, Rubella Vaccines In Kano

16 minutes ago

Insecurity: Ododo Tasks Kogi Residents On Intelligence Sharing

35 minutes ago
Load More

© 2025 Leadership Media Group - All Rights Reserved.

No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us

© 2025 Leadership Media Group - All Rights Reserved.