• Hausa Edition
  • Podcast
  • Conferences
  • LeVogue Magazine
  • Business News
  • Print Advert Rates
  • Online Advert Rates
  • Contact Us
Sunday, October 19, 2025
Leadership Newspapers
Read in Hausa
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us
No Result
View All Result
Leadership Newspapers
No Result
View All Result

Lagos-Calabar Coastal Road: FG To Build Shore Protection Against Flooding

by Kingsley Okoh
6 months ago
in News
Lagos-Calabar Coastal Road
Share on WhatsAppShare on FacebookShare on XTelegram

The federal government has said that plans were afoot to build retaining walls along Chainage 18 of the ongoing Lagos-Calabar coastal highway project to protect infrastructure from marine attacks, flooding and torrential waves coming from the shorelines.

Advertisement

Umahi made this known at the stakeholder engagement meeting organised by the Ministry of Works.
Umahi said,” We will do a shore protection base to prevent the water tides from eating into the infrastructure.”

He said retaining walls will be introduced to keep sand and protect against flooding due to flooding and sand usage, particularly since houses along the stretch have been submerged.

Advertisement

The Minister noted that the first phase of the highway is expected to be completed within 36 months, with 20 kilometres of the first section anticipated to be ready before the deadline.

The minister highlighted the significant investment and tourism opportunities that would be generated upon the completion of sections of the Lagos-Calabar Coastal Highway.

He said, “And, of course, we also have foreign investment in this project because 70 per cent of this project is dollar-based, on loans with as low as 2.5 per cent single-digit interest. We will toll the road, and Nigeria will recover all the money spent within 10 years.”

RELATED NEWS

Police Urge #FreeNnamdiKanu Protesters To Obey Court Order, Warn Against Violence

Anambra Guber: PVC Collection Exercise Begins October 22

Fear Of Protest Stops Nigerian Military From Seizing Power From Civilians — Sowore

2027: Aregbesola Slams APC, Declares ADC Nigeria’s Only Credible Alternative

Umahi commended Hitch Construction Company on the satisfactory progress of various construction processes, including dredging, excavation, dewatering, sand filling, and placement of crushed stone base.

He said, “We will continue to say that this project is in the most transparent form, and you can see the level of work being done. I was delighted when I entered section one and saw this road’s beauty. And I say, look, if the road of Earth can be like this, the coastal road can be, how beautiful it is. I’m happy with their progress. This project is a viable one that will generate revenue for the government,” he said.

Also, Dany Abboud, the managing director of Hitech Construction Company Limited, provided updates on the Lagos-Calabar Coastal Highway project.

According to Abboud, the team encountered challenges that required excavating 10 meters deep and are working to finalise designs to address the issues.

“The construction team is working diligently to complete the project, with 20 kilometres of the first section anticipated to be ready before the deadline. Marine engineers provide crucial information to structural engineers, who will submit their designs soon. Once approved, the project will continue with the necessary assessments,” he explained.

Join Our WhatsApp Channel

SendShare10172Tweet6357Share

OTHER NEWS UPDATES

Police Nab Man For Alleged Murder Of Farmer In Kwara
News

Police Urge #FreeNnamdiKanu Protesters To Obey Court Order, Warn Against Violence

3 hours ago
By-elections: Air Force Asks INEC To Settle Debts Before Poll Materials Airlift
News

Anambra Guber: PVC Collection Exercise Begins October 22

4 hours ago
Fear Of Protest Stops Nigerian Military From Seizing Power From Civilians — Sowore
News

Fear Of Protest Stops Nigerian Military From Seizing Power From Civilians — Sowore

5 hours ago
Advertisement
Leadership join WhatsApp

LATEST UPDATE

Police Urge #FreeNnamdiKanu Protesters To Obey Court Order, Warn Against Violence

3 hours ago

After Gaza War, Netanyahu To Seek Re-election

4 hours ago

Anambra Guber: PVC Collection Exercise Begins October 22

4 hours ago

Fear Of Protest Stops Nigerian Military From Seizing Power From Civilians — Sowore

5 hours ago

Imo Police Name Officers Involved Viral Cult Video

5 hours ago
Load More

© 2025 Leadership Media Group - All Rights Reserved.

No Result
View All Result
  • Home
  • News
  • Politics
  • Business
  • Sport
    • Football
  • Health
  • Entertainment
  • Education
  • Opinion
    • Editorial
    • Columns
  • Others
    • LeVogue Magazine
    • Conferences
    • National Economy
  • Contact Us

© 2025 Leadership Media Group - All Rights Reserved.